Certified in Risk and Information Systems Control (CRISC) — Question 40
After identifying new risk events during a project, the project manager's NEXT step should be to:
Answer options
- A. continue with a quantitative risk analysis
- B. determine if the scenarios need to be accepted or responded to
- C. continue with a qualitative risk analysis
- D. record the scenarios into the risk register
Correct answer: D
Explanation
The correct answer is D, as recording the new risk scenarios in the risk register is essential for tracking and managing those risks effectively. Options A and C suggest further analysis, which should occur after documenting the risks, while option B focuses on response strategies rather than initial documentation.