Certified in Risk and Information Systems Control (CRISC) — Question 399
An organization has initiated a project to launch an IT-based service to customers and take advantage of being the first to market. Which of the following should be of GREATEST concern to senior management?
Answer options
- A. The project is likely to deliver the product late.
- B. More time has been allotted for testing.
- C. A new project manager is handling the project.
- D. The cost of the project will exceed the allotted budget.
Correct answer: A
Explanation
The greatest concern for senior management should be the potential for late delivery, as being first to market is critical. Delays can jeopardize the competitive advantage. While budget overruns and personnel changes are important, they do not directly impact the timing of the product launch as significantly as a late delivery does.