Certified in Risk and Information Systems Control (CRISC) — Question 319
You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via. email every week. You have agreed and send reports every Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?
Answer options
- A. Configuration management
- B. Communications management
- C. Perform integrated change control process
- D. Project change control process
Correct answer: C
Explanation
The correct answer is C, as the 'Perform integrated change control process' is specifically designed to manage changes to the project, including assessing their impact and implementing them. Options A and B do not focus on the evaluation and approval of changes, while D, though related, is not the most precise term used in the context of integrated change management.