Which one of the following is the only output for the qualitative risk analysis process?
Answer options
- A. Project management plan
- B. Risk register updates
- C. Organizational process assets
- D. Enterprise environmental factors
Correct answer: B
Explanation
The correct answer is B, as the qualitative risk analysis process specifically results in updates to the risk register, which captures identified risks and their analysis. The other options are components of project management but are not outputs of the qualitative risk analysis process.