Which of the following would BEST provide early warning of a high-risk condition?
Answer options
- A. Risk assessment
- B. Key risk indicator (KRI)
- C. Risk register
- D. Key performance indicator (KPI)
Correct answer: B
Explanation
The Key Risk Indicator (KRI) is specifically designed to signal potential high-risk conditions before they escalate, making it the best option. In contrast, a Risk Assessment identifies risks, a Risk Register documents them, and a Key Performance Indicator (KPI) measures performance, but none serve the same early-warning purpose as a KRI.