Certified in Risk and Information Systems Control (CRISC) — Question 285
Which of the following is the MOST important reason to test new controls?
Answer options
- A. To verify controls work as intended.
- B. To justify the cost of control investment.
- C. To identify exceptions that elevate risk.
- D. To ensure an accurate and up-to-date controls register.
Correct answer: A
Explanation
The correct answer, A, highlights the necessity of confirming that controls function as expected to manage risks effectively. While options B, C, and D are also important, they are secondary to the primary goal of ensuring that controls are operational and effective in mitigating risks.