Certified in Risk and Information Systems Control (CRISC) — Question 261
From a risk management perspective, the PRIMARY objective of using maturity models is to enable:
Answer options
- A. solution delivery
- B. strategic alignment
- C. resource utilization
- D. performance evaluation
Correct answer: D
Explanation
The primary aim of using maturity models in risk management is to assess and enhance performance evaluation. While solution delivery, strategic alignment, and resource utilization are important, they are not the main focus of maturity models, which primarily concentrate on measuring and improving performance.