Certified in Risk and Information Systems Control (CRISC) — Question 229

There are four inputs to the Monitoring and Controlling Project Risks process. Which one of the following will NOT help you, the project manager, to prepare for risk monitoring and controlling?

Answer options

Correct answer: D

Explanation

The correct answer is D, Change requests, as they pertain to adjustments in project scope or objectives rather than directly aiding in the monitoring and controlling of risks. In contrast, the Risk register, Work Performance Information, and Project management plan provide essential data and context for evaluating risks throughout the project lifecycle.