Certified in Risk and Information Systems Control (CRISC) — Question 191

You are working as the project manager of the ABS project. The project is for establishing a computer network in a school premises. During the project execution, the school management asks to make the campus Wi-Fi enabled. You know that this may impact the project adversely. You have discussed the change request with other stakeholders. What will be your NEXT step?

Answer options

Correct answer: C

Explanation

The correct step is to analyze the impact (C) because understanding the potential consequences of the change is crucial before making any decisions. Updating the project management plan (A), issuing a change request (B), or updating the risk management plan (D) should come after assessing the impact to inform those actions.