Certified in Risk and Information Systems Control (CRISC) — Question 186
Which of the following is the MOST important component in a risk treatment plan?
Answer options
- A. Target completion date
- B. Treatment plan ownership
- C. Treatment plan justification
- D. Technical details
Correct answer: B
Explanation
The correct answer is B, Treatment plan ownership, as it designates responsibility for executing the risk treatment plan, ensuring accountability. The other options, while important, do not carry the same weight in terms of who is responsible for managing the risks effectively.