Certified in Risk and Information Systems Control (CRISC) — Question 183

What are the three PRIMARY steps to be taken to initialize the project?
Each correct answer represents a complete solution. (Choose three.)

Answer options

Correct answer: A, B, D

Explanation

The correct answers A, B, and D reflect essential steps in project initialization: conducting a feasibility study helps assess the project's viability, defining requirements clarifies what needs to be achieved, and planning risk management prepares for potential challenges. Option C, acquiring software, is not a primary initial step as it typically follows the defining of project scope and requirements.