Certified in Risk and Information Systems Control (CRISC) — Question 160

Which of the following is the GREATEST benefit to an organization when updates to the risk register are made promptly after the completion of a risk assessment?

Answer options

Correct answer: C

Explanation

The correct answer, C, is right because timely updates to the risk register lead to more informed and effective risk treatment decisions based on the latest assessment data. The other options, while beneficial, do not directly relate to the immediate impact on decision-making that comes from having an up-to-date risk register.