Certified in Risk and Information Systems Control (CRISC) — Question 153

You are the project manager of the GHY project for your company. This project has a budget of $543,000 and is expected to last 18 months. In this project, you have identified several risk events and created risk response plans. In what project management process group will you implement risk response plans?

Answer options

Correct answer: D

Explanation

The correct answer is D, Executing, because this is the phase where the planned activities, including risk responses, are actually implemented. The other options, such as Monitoring and Controlling and Planning, are related to different aspects of project management but do not involve the execution of risk responses.