Certified in Risk and Information Systems Control (CRISC) — Question 1432

Which of the following should be a risk practitioner’s GREATEST concern upon learning of failures in a data migration activity?

Answer options

Correct answer: A

Explanation

The integrity of data is the most critical factor during a data migration, as any inaccuracies can lead to significant operational issues. While system performance, cost overruns, and availability of test data are important considerations, they are secondary to ensuring that the data remains accurate and reliable throughout the migration process.