Certified in Risk and Information Systems Control (CRISC) — Question 1398
Which of the following is the PRIMARY factor in determining a recovery time objective (RTO)?
Answer options
- A. Response time of the emergency action plan
- B. Cost of downtime due to a disaster
- C. Cost of offsite backup premises
- D. Cost of testing the business continuity plan
Correct answer: B
Explanation
The correct answer, B, refers to the financial implications of downtime, which is crucial in setting the RTO. The other options, while important in their contexts, do not directly influence the RTO as significantly as the cost of downtime does.