Certified in Risk and Information Systems Control (CRISC) — Question 136

Fred is the project manager of a large project in his organization. Fred needs to begin planning the risk management plan with the project team and key stakeholders. Which plan risk management process tool and technique should Fred use to plan risk management?

Answer options

Correct answer: C

Explanation

The correct answer is C, as planning meetings and analysis are essential for developing a comprehensive risk management plan, allowing for collaborative input and thorough examination of potential risks. Options A and B focus more on collecting information rather than planning the management process, while option D pertains to evaluating project performance rather than risk planning.