Certified in Risk and Information Systems Control (CRISC) — Question 1345

The only output of qualitative risk analysis is risk register updates. When the project manager updates the risk register he will need to include several pieces of information including all of the following except for which one?

Answer options

Correct answer: B

Explanation

The risk probability-impact matrix is not part of the updates required for the risk register in qualitative risk analysis. Instead, the register should include trends, grouped risks, and a watchlist of low-priority risks, which help in managing and prioritizing the risks effectively.