Certified in Risk and Information Systems Control (CRISC) — Question 1338
You are the project manager of GHT project. A risk event has occurred in your project and you have identified it. Which of the following tasks you would do in reaction to risk event occurrence? Each correct answer represents a part of the solution. (Choose three.)
Answer options
- A. Monitor risk
- B. Maintain and initiate incident response plans
- C. Update risk register
- D. Communicate lessons learned from risk events
Correct answer: A, B, D
Explanation
The correct actions after a risk event occur include monitoring the risk to assess its impact (A), maintaining and initiating incident response plans to address the issue (B), and communicating lessons learned to improve future risk management (D). Updating the risk register (C) is not an immediate response to a risk event, but rather part of ongoing risk management.