You are the project manager of GHT project. A risk event has occurred in your project and you have identified it. Which of the following tasks you would do in reaction to risk event occurrence? Each correct answer represents a part of the solution. (Choose three.)

Answer options

Correct answer: A, B, D

Explanation

The correct actions after a risk event occur include monitoring the risk to assess its impact (A), maintaining and initiating incident response plans to address the issue (B), and communicating lessons learned to improve future risk management (D). Updating the risk register (C) is not an immediate response to a risk event, but rather part of ongoing risk management.