Certified in Risk and Information Systems Control (CRISC) — Question 1314
What activity should be done for effective post-implementation reviews during the project?
Answer options
- A. Establish the business measurements up front
- B. Allow a sufficient number of business cycles to be executed in the new system
- C. Identify the information collected during each stage of the project
- D. Identify the information to be reviewed
Correct answer: A
Explanation
The correct answer, A, emphasizes the importance of defining business measurements early to assess the project's success effectively. Options B, C, and D focus on post-implementation activities rather than the preparatory steps necessary for a successful review.