Certified in Risk and Information Systems Control (CRISC) — Question 131
What are the various outputs of risk response?
Answer options
- A. Risk Priority Number
- B. Residual risk
- C. Risk register updates
- D. Project management plan and Project document updates
- E. Risk-related contract decisions
Correct answer: B, C, D
Explanation
The correct answers B, C, and D represent the outcomes of risk response activities, as they directly relate to how risks are managed and recorded in project documentation. Option A, Risk Priority Number, is a metric used to assess risks rather than an output of risk response, and option E, Risk-related contract decisions, is more about contractual agreements than the direct results of risk response efforts.