Certified in Risk and Information Systems Control (CRISC) — Question 131

What are the various outputs of risk response?

Answer options

Correct answer: B, C, D

Explanation

The correct answers B, C, and D represent the outcomes of risk response activities, as they directly relate to how risks are managed and recorded in project documentation. Option A, Risk Priority Number, is a metric used to assess risks rather than an output of risk response, and option E, Risk-related contract decisions, is more about contractual agreements than the direct results of risk response efforts.