Certified in Risk and Information Systems Control (CRISC) — Question 1295
You are the project manager of the PFO project. You are working with your project team members and two subject matter experts to assess the identified risk events in the project. Which of the following approaches is the best to assess the risk events in the project?
Answer options
- A. Interviews or meetings
- B. Determination of the true cost of the risk event
- C. Probability and Impact Matrix
- D. Root cause analysis
Correct answer: A
Explanation
The correct approach, 'Interviews or meetings', allows for direct communication and detailed discussion of risks with both the project team and subject matter experts. While the other options provide valuable insights, they may not allow for the same level of collaborative assessment and real-time feedback that interviews and meetings facilitate.