After automated controls have been implemented and tested, which of the following is MOST useful to perform?
Answer options
- A. Continuous control monitoring
- B. Internal audit review
- C. Control self-assessment (CSA)
- D. Cost-benefit analysis
Correct answer: A
Explanation
Continuous control monitoring is essential after implementing automated controls, as it ensures that these controls are functioning correctly over time. While internal audits, control self-assessments, and cost-benefit analyses are important, they do not provide the ongoing oversight necessary to promptly identify and rectify any issues with the automated controls.