Certified in Risk and Information Systems Control (CRISC) — Question 1280

After automated controls have been implemented and tested, which of the following is MOST useful to perform?

Answer options

Correct answer: A

Explanation

Continuous control monitoring is essential after implementing automated controls, as it ensures that these controls are functioning correctly over time. While internal audits, control self-assessments, and cost-benefit analyses are important, they do not provide the ongoing oversight necessary to promptly identify and rectify any issues with the automated controls.