Certified in Risk and Information Systems Control (CRISC) — Question 1261
Which of the following is the MOST effective way to help ensure a risk treatment plan remains on track?
Answer options
- A. Documenting risk treatment procedures for relevant stakeholders
- B. Adopting an agile project management approach
- C. Requiring approval by the second line of defense
- D. Assigning sufficient resources to implement the plan
Correct answer: D
Explanation
The correct answer is D because having sufficient resources is crucial for effectively implementing a risk treatment plan. While documenting procedures and requiring approvals are important, they do not guarantee that the plan can be executed properly without the necessary resources. An agile approach can aid in flexibility but does not directly address the essential need for resources.