You work as the project manager for Bluewell Inc. Your project has several risks that will affect several stakeholder requirements. Which project management plan will define who will be available to share information on the project risks?

Answer options

Correct answer: D

Explanation

The correct answer is D, the Communications Management Plan, as it specifies how information regarding project risks will be communicated to stakeholders. The Resource Management Plan focuses on resource allocation, the Risk Management Plan deals with identifying and analyzing risks, and the Stakeholder management strategy outlines how to engage stakeholders, but does not specifically address communication of risks.