Certified in Risk and Information Systems Control (CRISC) — Question 1231
Which of the following is the MOST appropriate key performance indicator (KPI) to measure change management performance?
Answer options
- A. Percentage of rejected change requests
- B. Percentage of changes implemented successfully
- C. Number of after-hours emergency changes
- D. Number of change control requests
Correct answer: B
Explanation
The correct answer is B, as the percentage of changes implemented successfully directly indicates how effectively the change management process is functioning. Options A, C, and D do not accurately measure the success of the change management process, focusing instead on negative outcomes or activity counts that do not reflect performance.