Which of the following is the MOST appropriate key performance indicator (KPI) to measure change management performance?

Answer options

Correct answer: B

Explanation

The correct answer is B, as the percentage of changes implemented successfully directly indicates how effectively the change management process is functioning. Options A, C, and D do not accurately measure the success of the change management process, focusing instead on negative outcomes or activity counts that do not reflect performance.