Certified in Risk and Information Systems Control (CRISC) — Question 11

You work as a project manager for BlueWell Inc. You are preparing for the risk identification process. You will need to involve several of the project's key stakeholders to help you identify and communicate the identified risk events. You will also need several documents to help you and the stakeholders identify the risk events. Which one of the following is NOT a document that will help you identify and communicate risks within the project?

Answer options

Correct answer: D

Explanation

The correct answer is D, as a Risk Register is specifically designed to identify and communicate risks within a project. In contrast, Stakeholder registers, Activity duration estimates, and Activity cost estimates are documents that provide information about project stakeholders and project execution but do not directly pertain to risk identification.