Certified in Risk and Information Systems Control (CRISC) — Question 1089
Which of the following is MOST helpful in reducing the likelihood of inaccurate risk assessment results?
Answer options
- A. Having internal audit validate control effectiveness
- B. Updating organizational risk tolerance levels
- C. Reviewing the applicable risk assessment methodologies
- D. Involving relevant stakeholders in the risk assessment process
Correct answer: D
Explanation
Involving relevant stakeholders in the risk assessment process ensures that diverse perspectives and insights are considered, which leads to a more comprehensive evaluation of risks. The other options, while beneficial, do not directly address the collaborative aspect that is crucial for accurate risk assessment results.