Certified in Risk and Information Systems Control (CRISC) — Question 1076

You are the project manager of HGT project. You are in the first phase of the risk response process and are doing following tasks :
Communicating risk analysis results
Reporting risk management activities and the state of compliance
Interpreting independent risk assessment findings
Identifying business opportunities
Which of the following process are you performing?

Answer options

Correct answer: A

Explanation

The correct answer is A, Articulating risk, as this involves communicating and interpreting risk analysis results and findings. The other options do not accurately reflect the tasks being performed; mitigating risk focuses on reducing risk, tracking risk involves monitoring ongoing risks, and reporting risk is more about documenting than the broader communication of risk analysis.