You are working as a project manager in Bluewell Inc. You are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. For your project archives, which one of the following is an output of risk monitoring and control?
Answer options
- A. Qualitative risk analysis
- B. Risk audits
- C. Quantitative risk analysis
- D. Requested changes
Correct answer: D
Explanation
The correct answer is D, as requested changes are a direct output of the risk monitoring and controlling process, reflecting adjustments based on identified risks. Options A, B, and C refer to types of risk analysis and audits, which are inputs or processes rather than direct outputs from risk monitoring and control.