Certified in Risk and Information Systems Control (CRISC) — Question 1063
Which of the following baselines identifies the specifications required by the resource that meet the approved requirements?
Answer options
- A. Functional baseline
- B. Allocated baseline
- C. Product baseline
- D. Developmental baseline
Correct answer: B
Explanation
The Allocated baseline is the correct answer because it specifies the requirements that must be met by various resources. The other baselines, such as Functional, Product, and Developmental, do not focus specifically on resource specifications aligned with approved requirements.