You work as a project manager for BlueWell Inc. You are preparing to plan risk responses for your project with your team. How many risk response types are available for a negative risk event in the project?
Answer options
- A. 5
- B. 7
- C. 1
- D. 4
Correct answer: D
Explanation
The correct answer is D, as there are four recognized response strategies for negative risks: avoid, transfer, mitigate, and accept. Options A and B are incorrect because they suggest an incorrect number of strategies, while option C is incorrect as it implies there is only one strategy available.