Certified in Risk and Information Systems Control (CRISC) — Question 1022
You are the project manager of GHT project. You have applied certain control to prevent the unauthorized changes in your project. Which of the following control you would have applied for this purpose?
Answer options
- A. Personnel security control
- B. Access control
- C. Configuration management control
- D. Physical and environment protection control
Correct answer: C
Explanation
Configuration management control is essential for tracking and managing changes in project deliverables, ensuring that only authorized modifications are made. While personnel security control, access control, and physical and environmental protection are important for overall security, they do not specifically address the management of project configurations and changes.