Certified in Risk and Information Systems Control (CRISC) — Question 1005

You are working with a vendor on your project. A stakeholder has requested a change for the project, which will add value to the project deliverables. The vendor that you're working with on the project will be affected by the change. What system can help you introduce and execute the stakeholder change request with the vendor?

Answer options

Correct answer: A

Explanation

The correct answer is A, as a Contract change control system specifically addresses modifications to contractual agreements, which is essential when a vendor is involved. Options B, C, and D pertain to different aspects of project management and do not directly relate to managing changes with a vendor's contract.