Certified in Risk and Information Systems Control (CRISC) — Question 1005
You are working with a vendor on your project. A stakeholder has requested a change for the project, which will add value to the project deliverables. The vendor that you're working with on the project will be affected by the change. What system can help you introduce and execute the stakeholder change request with the vendor?
Answer options
- A. Contract change control system
- B. Scope change control system
- C. Cost change control system
- D. Schedule change control system
Correct answer: A
Explanation
The correct answer is A, as a Contract change control system specifically addresses modifications to contractual agreements, which is essential when a vendor is involved. Options B, C, and D pertain to different aspects of project management and do not directly relate to managing changes with a vendor's contract.