COBIT 5 Foundation — Question 74
What Programme Management component in the implementation Life Cycle is linked to embedding the new approaches?
Answer options
- A. Realise benefits
- B. Review effectiveness
- C. Plan programme
- D. Execute the plan
Correct answer: A
Explanation
The correct answer is A, as 'Realise benefits' focuses on embedding new approaches to ensure they deliver value. The other options, while important, relate to assessing outcomes, planning, or executing rather than the specific integration of new methods.