COBIT 5 Foundation — Question 62
Which of the following criteria must be met for a process to meet a higher capability level?
Answer options
- A. An identified subset of the activities of that level can be executed effectively
- B. All activities of that level are successfully performed
- C. Capability is demonstrated on the most relevant process activities
Correct answer: B
Explanation
The correct answer is B because a process must successfully perform all activities at the higher capability level to qualify. Option A is incorrect as executing only a subset does not satisfy the criteria for a higher level, and option C is misleading since demonstrating capability on relevant activities alone is insufficient without completing all activities.