COBIT 5 Foundation — Question 19
What is the name of the Change Enablement life cycle Phase which supports Phase 4. What needs to be done?
Answer options
- A. Identify role players
- B. Define target state
- C. Plan program
- D. Define problems and opportunities
Correct answer: A
Explanation