COBIT 2019 Foundation — Question 90

Which COBIT domain of management objectives incorporates managed business process controls?

Answer options

Correct answer: A

Explanation

The correct answer is A, as the Build, Acquire and Implement (BAI) domain specifically deals with the management objectives related to the development and implementation of business processes and controls. Options B and C, Align, Plan and Organize (APO) and Deliver, Service and Support (DSS), focus on planning and ongoing service delivery, respectively, and do not primarily address managed business process controls.