COBIT 2019 Foundation — Question 90
Which COBIT domain of management objectives incorporates managed business process controls?
Answer options
- A. Build, Acquire and Implement (BAI)
- B. Align, Plan and Organize (APO)
- C. Deliver, Service and Support (DSS)
Correct answer: A
Explanation
The correct answer is A, as the Build, Acquire and Implement (BAI) domain specifically deals with the management objectives related to the development and implementation of business processes and controls. Options B and C, Align, Plan and Organize (APO) and Deliver, Service and Support (DSS), focus on planning and ongoing service delivery, respectively, and do not primarily address managed business process controls.