COBIT 2019 Foundation — Question 85
Which of the following criteria must be met for a process to meet a higher capability level?
Answer options
- A. All activities of that level are successfully performed.
- B. Capability is demonstrated on the most relevant process activities.
- C. An identified subset of the activities of that level can be executed effectively.
Correct answer: A
Explanation
Option A is correct because achieving a higher capability level requires all activities at that level to be performed successfully. Option B is incorrect as it only requires capability in relevant activities, not all. Option C also fails because it allows for only a subset of activities to be effective, which does not satisfy the criteria for a higher capability level.