COBIT 2019 Foundation — Question 7
COBIT defines stakeholder value creation as which of the following?
Answer options
- A. Realization of benefits at a controlled resource cost while controlling risk
- B. Realization of benefits at an optimal resource cost while optimizing risk
- C. Realization of benefits at a reduced resource cost while mitigating risk
Correct answer: B
Explanation
The correct answer, B, emphasizes achieving benefits efficiently while also optimizing risk management, which is central to stakeholder value creation in COBIT. Option A focuses on controlled resource costs but does not highlight optimization, while option C mentions reducing resource costs without addressing the importance of risk optimization.