COBIT 2019 Foundation — Question 61
Which of the following should be scheduled for completion FIRST when prioritizing improvement initiatives?
Answer options
- A. Initiatives that are the least expensive in order to lower risk due to failure
- B. Initiatives with the lowest cost regardless of expected business value
- C. Initiatives that are easiest to achieve and will garner business benefits
Correct answer: C
Explanation
The correct answer is C because focusing on initiatives that are easy to execute and offer business benefits ensures quick wins and boosts morale. Options A and B do not consider the potential business impact and may delay valuable improvements by focusing solely on cost.