Which of the following is ESSENTIAL to help ensure that a project's benefits are identified and continually monitored?

Answer options

Correct answer: A

Explanation

A well-developed business case is fundamental as it outlines the expected benefits and serves as a reference for monitoring them throughout the project. While earned value management reporting and stage gate reviews are important for project management, they do not specifically focus on the identification and ongoing monitoring of benefits.