Certified Information Security Manager (CISM) — Question 289
Which of the following MOST effectively allows for disaster recovery testing without interrupting business operations?
Answer options
- A. Structured walk-through
- B. Simulation testing
- C. Parallel testing
- D. Full interruption testing
Correct answer: C
Explanation
Parallel testing is the correct choice because it allows the disaster recovery plan to be tested in a live environment without disrupting ongoing business activities. In contrast, full interruption testing halts operations, while structured walk-through and simulation testing do not provide real-time validation of the recovery process.