Certified Information Systems Auditor (CISA) — Question 976
Which of the following BEST facilitates strategic program management?
Answer options
- A. Aligning projects with business portfolios
- B. Implementing stage gates
- C. Establishing a quality assurance (QA) process
- D. Tracking key project milestones
Correct answer: A
Explanation
Aligning projects with business portfolios ensures that the projects undertaken are directly contributing to the overall strategic goals of the organization, making it the best option. The other options, while important for project management, do not directly influence the alignment of projects with strategic objectives.