Certified Information Systems Auditor (CISA) — Question 91
Which of the following should be an IS auditor’s GREATEST concern when reviewing an organization’s capacity management planning?
Answer options
- A. Many of the resource requirements are based on estimates
- B. The organization is increasingly dependent on the use of cloud providers
- C. Some planning areas are not well developed
- D. Current resource utilization is not monitored
Correct answer: D
Explanation
The correct answer is D because without monitoring current resource utilization, the organization may face performance issues and inefficiencies. While A, B, and C are valid concerns, they are secondary to the critical need for proper monitoring of resource utilization to ensure capacity aligns with demand.