Certified Information Systems Auditor (CISA) — Question 838
What is the BEST method to determine if IT resource spending is aligned with planned project spending?
Answer options
- A. Return on investment (ROI) analysts
- B. Critical path analysis
- C. Earned value analysis (EVA)
- D. Gantt chart
Correct answer: C
Explanation
The correct answer is Earned value analysis (EVA), as it integrates project scope, schedule, and cost metrics to provide a clear picture of project performance. The other options, while useful in different contexts, do not specifically evaluate the alignment of spending against planned project budgets.