Certified Information Systems Auditor (CISA) — Question 812
Which of the following provides the BEST evidence of effective IT portfolio management?
Answer options
- A. Programs in the IT portfolio are prioritized by each business function.
- B. The IT portfolio is updated on the basis of current industry benchmarks.
- C. The IT portfolio is updated as business strategy changes.
- D. IT portfolio updates are communicated when approved.
Correct answer: C
Explanation
Option C is correct because an effective IT portfolio management should align closely with the evolving business strategy to ensure that IT resources are utilized effectively. The other options, while relevant, do not directly indicate a proactive approach to managing the IT portfolio in response to business strategy changes.