Certified Information Systems Auditor (CISA) — Question 782
Which of the following audit findings should be given the HIGHEST priority?
Answer options
- A. IT key risk indicators (KRIs) are calculated internally by the IT team.
- B. The organization's IT investment exceeds industry benchmarks.
- C. IT key risk indicators (KRIs) are not periodically reviewed.
- D. The board’s agenda does not include the progress of IT projects.
Correct answer: C
Explanation
The correct answer is C because failing to periodically review IT key risk indicators (KRIs) can lead to unaddressed vulnerabilities and risks that may impact the organization significantly. Options A and B, while important, do not directly affect the risk management process as critically as option C. Option D is also relevant, but it pertains more to governance than immediate risk assessment.