Certified Information Systems Auditor (CISA) — Question 643

Which of the following is the PRIMARY concern when negotiating a contract for a hot site?

Answer options

Correct answer: B

Explanation

The correct answer, B, emphasizes the necessity for the hot site to be available during multiple disaster declarations, which is crucial for business continuity. While options A, C, and D are important aspects of disaster recovery planning, they do not take precedence over the immediate availability of the site when it is most needed.