Certified Information Systems Auditor (CISA) — Question 496
When conducting a requirements analysis for a project, the BEST approach would be to:
Answer options
- A. conduct a control self-assessment (CSA).
- B. test operational deliverables.
- C. prototype the requirements.
- D. consult key stakeholders.
Correct answer: D
Explanation
Consulting key stakeholders is essential as they provide valuable insights and ensure the requirements align with business needs. Options A, B, and C may contribute to the process but do not directly address the foundational understanding of requirements like stakeholder consultation does.