Certified Information Systems Auditor (CISA) — Question 48
Reviewing project plans and status reports throughout the development life cycle will:
Answer options
- A. eliminate the need to perform a risk assessment.
- B. postpone documenting the project's progress until the final phase.
- C. guarantee that the project will meet its intended deliverables.
- D. facilitate the optimal use of resources over the life of the project.
Correct answer: D
Explanation
Option D is correct because regular reviews help in resource allocation and management, ensuring they are used effectively. Option A is incorrect as risk assessments are still necessary regardless of project reviews. Option B is wrong because documenting progress should occur throughout the project, not just at the end. Option C is not guaranteed since reviews do not ensure deliverables are met, but they do help track progress.